TRENCHLESS INSTALLATION

JACKING METHOD 1: AUGER METHOD

  • Soil cutting at the face by the bore head and soil removal by means of continous flight of augers
  • Augers run in a separate guiding pipe
  • Better suited for cohesive soils
  • Recommended jacking span between 60m to 75m (Max length ~ 100m)

TRENCHLESS INSTALLATION

JACKING METHOD 2: SLURRY METHOD

  • Tunnel face is supported mechanically or by a pressurized slurry
  • Spoil (cuttings) removed hydraulically in the form of a slurry
  • Cutting head designs depends on soil or rock type
  • Recommended for longer jacking span exceeding 100m